Middlesex, Vermont · Capital Improvement Plan · FY2028–FY2042
How Middlesex pays for its machines.
The town finances its trucks, fire engines, buildings, and roads one note at a time while its reserve funds sit apart. This page shows that pattern in the town's own numbers, then six ways to fund the same fifteen-year schedule — modeled year by year from the capital plan and audited financials. A modeling exercise by Matt Rkiouak, Budget Committee member; not adopted policy.
Middlesex owns a fleet of trucks, fire engines, buildings, and paved roads that wear out on a
schedule the town has already written down — at today's market prices, about $5.9 million
of local spending over the next fifteen years, net of the paving grants it expects. Every dollar figure on this page is in
today's dollars: no general inflation is assumed. Future bills will be higher by whatever
inflation brings — for every plan alike, with home values and the grand list rising
alongside, so the comparisons stand. That figure counts only what the town can already see: the machines it owns
today, on the cycles they have run, plus the five-year culvert plan the regional planning
commission delivered in July 2026. Fifteen years will add needs no one has priced yet, and
every one of them arrives on top of the numbers here. How to pay is a choice, and the town's
recent choices have a pattern. It starts with one machine.
In March 2024 the town voted to buy an excavator. The article authorized up to $200,000,
financed over as long as fifteen years; that July the Select Board signed a $182,000 note at
5.97%, repaid in equal annual slices of principal plus interest on what remains. By the final
payment in 2035 the note will have cost about $69,000 in interest. By the end of that first fiscal year, the reserve
fund kept for exactly this kind of machine held half the purchase price — earning 0.7% while
the note beside it charged 5.97%.
The excavator note, year by yearPrincipal in green — equal slices of the loan — plus interest, in amber, on what remains. $251,251 to buy a $182,000 machine.Payment table
FY
Principal
Interest
Still owed
2025
$2,300
$10,865
$179,700
2026
$18,200
$10,728
$161,500
2027
$18,200
$9,642
$143,300
2028
$18,200
$8,555
$125,100
2029
$18,200
$7,468
$106,900
2030
$18,200
$6,382
$88,700
2031
$18,200
$5,295
$70,500
2032
$18,200
$4,209
$52,300
2033
$18,200
$3,122
$34,100
2034
$18,200
$2,036
$15,900
2035
$15,900
$949
$0
Warned article · March 2024 · Approved
“Shall the Town voters authorize the Select Board to purchase a new excavator in an amount not to exceed $200,000 to be financed over a period not to exceed 15 years? (24 V.S.A. §1786a(c))”
Meanwhile, the Asset & Equipment Fund — the reserve kept for exactly this kind of machine —
$50,033
start of FY2025
→
$100,463
end of FY2025
grew, and bought nothing. It held half the machine's price — and under its warned purpose it could have paid for nothing else anyway.
$69,251
interest over the note's life, at 5.97% — while the fund beside it earned 0.7%
Every large machine the town runs was bought the same way: vote, sign, pay for years. The
grader (2021), the Kenworth dump truck (2022), the Lo Pro truck (2019), the fire tanker
(2019), and the fire station itself (a 2015 bond) each left a note behind. Alongside the
notes, the town keeps six reserve funds, each bound by Vermont law (24 V.S.A. § 2804) to the
purpose voters gave it — the Asset & Equipment Fund cannot fix the Town Hall roof. The funds
are real money, $341,657 at mid-2025. But the pattern rarely lets them buy anything: in
fiscal 2025 the town spent $258,327 on capital purchases and debt payments against a budgeted
capital line of $126,000, with the difference covered by financing and one-off draws.
A decade of notesEvery large purchase since 2015 and the years its payments run. Faded bars are paid off. The vertical rule is today.
Public WorksFire DepartmentBuildings
The six reserve funds, 6/30/2025 — each spendable only on its voted purpose.
Each signature leaves a payment schedule behind, and the schedules stack. In fiscal 2026 the
machine notes cost about $182,000 in principal and interest — five notes and a bond at once.
The stack thins as notes mature: about $97,000 by FY2028, about $47,000 by FY2031, with the
excavator running to FY2035 and the grader to FY2036. The flood-recovery debt — about $466,000 a year
through FY2031 — sits on top of all of this and is identical under every plan on this page.
It is a bridge, not a lasting burden: the town expects FEMA reimbursement to clear it by
about FY2029, and the charted line is its contractual worst case.
The payments those signatures left behindDebt service on the town's machine notes, fiscal 2026–2036. Each column is a year's payments; each color one note.
One number states where the pattern leaves the town as the planning window opens. Entering
fiscal 2028, the six reserve funds hold $341,657 while the three debts still running — the
excavator and grader notes and the fire-station bond — carry $446,900 of remaining balance. The town's capital
accounts are $105,243 short of its capital debts.
−105,243
what Middlesex owns for capital, minus what it still owes on its machines, entering fiscal 2028
Three facts make the coming window different from the decade behind it. The bills are
front-loaded: the overdue trucks, both fire-engine orders, the Shady Rill road project, and
the five-year culvert plan all land by FY2032. Fire apparatus is bought years before it arrives: contracts sign
roughly three years ahead of delivery, the price locks at signing, and prices have been
rising about 7% a year. And the schedule is a floor, not a forecast: it lists only what is
known today. The needs the town cannot yet see will land on top of it — under the borrowing
plans, as interest on an already larger debt.
The culvert plan is the newest line on the schedule. In the summer of 2025 the Central Vermont
Regional Planning Commission inventoried every culvert in the town's road right-of-way and
found 142 rated closed, urgent, critical or poor. Its July 2026 replacement plan works outward
from the trunk roads — Center, Molly Supple Hill and East Hill first — at the road crew's pace
of roughly 30 culverts a year, and prices the pipe at about $157,000 over FY2028–FY2032, between
$26,000 and $37,000 a year in today's dollars. The model pays it from the Bridge fund as a
cash line, never financed; the crew's installation labor stays in the highway operating budget.
The schedule every plan faces, FY2028–FY2042Local share of each year's capital events at market-adjusted prices (net of the Class 2 paving grants), booked when the money is committed — apparatus at contract signing, roughly three years before delivery. The bills are front-loaded: the overdue trucks, both engine orders, the Shady Rill project, and the five-year culvert replacement plan all land by FY2032. Waiting does not defer these bills; it raises them: ordering Engine 1 three years later would add about $181,000 to its locked price.
Every scheduled event, both price bases (table)
FY
Item
Category
Market price
Grant
2028
Shady Rill section 1
Paving
$652,333
$521,866
2028
International 10-wheeler dump (backlog)
Public Works Vehicles
$246,500
2028
Caterpillar backhoe
Public Works Vehicles
$153,000
2028
Komatsu loader (backlog)
Public Works Vehicles
$148,750
2028
Culvert replacement plan
Culverts
$35,939
2028
Overhead doors (3) (backlog)
Town Shed
$11,000
2028
Engine 6
Fire Dept Vehicles
$655,398
2029
Freightliner 6-wheeler dump (backlog)
Public Works Vehicles
$238,000
2029
Pickup with plow
Public Works Vehicles
$68,000
2029
Culvert replacement plan
Culverts
$36,552
2029
Server (mechanical)
Town Hall
$20,000
2029
Overhead doors
Fire Station
$11,000
2030
Kenworth dump truck
Public Works Vehicles
$178,500
2030
Culvert replacement plan
Culverts
$29,164
2030
Exterior windows
Town Hall
$25,000
2030
Engine 1
Fire Dept Vehicles
$802,891
2031
Culvert replacement plan
Culverts
$29,265
2031
Town server replacement
Town Hall
$20,000
2031
Tanker
Fire Dept Vehicles
$429,547
2032
Culvert replacement plan
Culverts
$26,177
2032
Boiler
Town Hall
$20,000
2032
Interior painting/flooring
Town Hall
$9,000
2033
Fuel tank
Town Shed
$8,500
2035
International 10-wheeler dump
Public Works Vehicles
$246,500
2035
Town server replacement
Town Hall
$20,000
2035
Rescue
Fire Dept Vehicles
$450,438
2036
Grader
Public Works Vehicles
$289,000
2037
Freightliner 6-wheeler dump
Public Works Vehicles
$238,000
2037
Pickup with plow
Public Works Vehicles
$68,000
2037
Exterior painting
Town Hall
$12,000
2038
Kenworth dump truck
Public Works Vehicles
$178,500
2039
Shady Rill section 2
Paving
$296,515
$237,212
2040
Kobelco excavator
Public Works Vehicles
$170,000
2040
Komatsu loader
Public Works Vehicles
$148,750
2040
HVAC
Fire Station
$15,000
2042
International 10-wheeler dump
Public Works Vehicles
$246,500
2042
Roof
Town Hall
$25,000
Routine paving ($30,000 every year) is omitted from the table but included in the chart and all models. The culvert replacement plan is the CVRPC 2026 Road Improvement Plan's five-year budget for pipe, paid from the Bridge fund; the road crew's installation labor sits in the highway operating budget. Apparatus rows show the contract-locked price (sheet price escalated 7%/yr from its 2023 vintage to order year); the committee's original sheet prices are in the downloadable workbook and CSVs.
The order dates, not the delivery dates, are the deadlines.
The order clock: waiting has a priceA fire truck's price locks when the contract is signed, about three years before delivery, and rises roughly 7% for every year of waiting. Slide the order later to see the locked price move.
Ordered on schedule (FY2030), the Engine 1 locks at $802,891.
Every plan below buys the identical equipment over FY2028–FY2042, on the town's real fund
structure, at market prices, under Vermont borrowing law. Three rules shape all of them:
Bonds sized to be spent. Federal tax law effectively forbids parking tax-exempt bond
proceeds: an issuer must expect to spend 85% within three years to invest them without
yield restriction, and 85% within five to keep the interest tax-exempt at all. Each plan
therefore bundles its borrowing into a bond sized to the FY2028–31 crunch; plans that
bond the mid-2030s Rescue order ask a second, smaller question when it lands (the step-up
and full pre-funding plans cover it without one). Bond Bank access is not a constraint —
pooled sales run twice a year, carry no fees, and the Bank lent to Middlesex four times in
fourteen months at the peak of its flood borrowing. What each question spends is voter
goodwill: the town's last bond question, $2.5 million for the town hall in November 2024,
failed 610–534. A single consolidated bond that avoided the second question by parking
twelve years of proceeds at 0.7% while paying 4% is priced in the stress tests.
Heavy trucks stay out of the bond. Manufacturers' municipal installment programs
finance them at about 5.5% on five-year terms, by ordinary warned article.
Reserves earn 0.7%. That is the town's realized FY2025 yield, computed from the audit —
in a year when Vermont money markets paid 3–5%. Moving the money to a market-rate account
is tested separately in the stress tests.
At market prices, current practice is not the cheap option: it averages about $478,000 a year
over the window and peaks near $640,000, as financed market-priced engines stack twelve-year
notes on seven-year trucks. The town will pay capital bills of this size under every plan;
the choice is what fifteen years of them leave behind. In absolute terms the plans ask
between $127 and $146 a year per $100,000 of home market value — on a $300,000 home, they
differ by at most a few hundred dollars a year. Every figure prices known needs only;
whatever the window adds lands on top. The shaded years beyond FY2042 in
the charts are a projection — the same machines recurring on their lifecycles — showing
where each structure settles: the pre-funded ask falls toward the replacement bill with no
interest in it, while the borrowing structures keep financing each cycle.
Plan explorer
The annual capital budgetWhat this plan asks taxpayers for capital each year; the other five in gray.
Interest paid to lendersCumulative taxes lost to interest. Dashed years: the window's remaining debt service plus each structure's new borrowing as the cycle repeats.
What the town owns minus what it owesEvery plan departs the same point: −$105,243 entering FY2028. The line counts every reserve fund, including Court Resurfacing, which has no scheduled work — so it overstates usable position, and current practice most, because it alone keeps funding it.
Yearly capital taxes per $100,000 of home valueThe capital budget translated to a home's tax bill (market value, via the CLA).
Solid lines are the modeled window. Dashed, shaded years (FY2043–52) are projected: the same machines recurring on their lifecycles at today's prices — committed plan levels expire with the window, and each single-budget structure levies one flat ask covering the decade's requirement, with the funds absorbing the timing. The pre-funded ask falls to the replacement bill with no interest in it; the borrowing structures keep financing each cycle. All figures, including the projection, are in today's dollars — no general inflation is assumed; future bills rise with it for every plan alike.
Current practice
The town's recent pattern: an inconsistent capital line, funds that sometimes pay and sometimes sit, and full financing for the rest.
The capital appropriation wobbles between $126,000 and $101,000 as it has in recent budgets; a reserve fund pays for an item only when it covers the whole price, as the audit shows; everything else is financed in full — the truck fleet through vendor installment programs, fire apparatus and paving through the plan's capital-program bonds — with debt service riding the tax bill. The culvert plan is paid from the Bridge fund in the years its balance covers the year's pipe, and from the tax bill otherwise. It also keeps feeding the Court Resurfacing fund, which has no scheduled work in the window, and that flatters the position this plan ends with: about $91,000 of its closing balance cannot buy anything on the schedule, so the −$130,000 shown above is nearer −$221,000 of usable capital position, and under 24 V.S.A. § 2804 the money cannot be turned to another purpose without a warned article. Every plan carries the same $18,000 opening balance in that fund; only current practice keeps adding to it.
Raised in taxes, 15 yrs$7.16M
Borrowed$4.51M
Interest paid$997k
Capital taxes average $478k/yr — $130/yr per $100,000 of home value · True cost $7.27M · bonds of $1.89M + $450k · ends 2042 at −$130k owns−owes · FY2028 change on a $300,000 home: −$37/yr (−1.9¢ on the rate)
Save $50,000 more a year
The smallest genuine change: current practice plus a $50,000 annual seed, steered to where the need is.
Same structure as current practice — debt service on the tax bill — but the fund is drawn toward each purchase before borrowing, and the Select Board steers contributions annually to the funds with upcoming needs.
Raised in taxes, 15 yrs$7.01M
Borrowed$3.27M
Interest paid$807k
Capital taxes average $468k/yr — $127/yr per $100,000 of home value · True cost $7.04M · bonds of $1.79M + $222k · ends 2042 at −$113k owns−owes · FY2028 change on a $300,000 home: +$4/yr (+0.2¢ on the rate)
Phased start from $300k (reaches $480k in FY2032)
Begin at $300,000 and climb steeply to the break-even budget of $480,000 by FY2032.
Because apparatus contracts sign years before delivery, the spending crunch sits at the front of this window — so a phased start only works with steep steps, peaking near $681,000 mid-climb before settling. Starting low defers cost at interest.
Raised in taxes, 15 yrs$7.27M
Borrowed$3.62M
Interest paid$860k
Capital taxes average $485k/yr — $132/yr per $100,000 of home value · True cost $7.12M · bonds of $1.71M + $428k · ends 2042 at $87k owns−owes · FY2028 change on a $300,000 home: +$26/yr (+1.3¢ on the rate)
Break even by 2042 ($480k/yr)
A steady $480,000 capital budget — the smallest at which the town owns as much as it owes by 2042.
One annual capital budget inside the budget article, allocated by the Select Board across the existing purpose funds (no new articles needed); the equipment funds pay the equipment notes. Solving for the smallest levy is not solving for cost: the seed plan runs about $80,000 cheaper all in, and every larger steady budget costs less in the end.
Raised in taxes, 15 yrs$7.23M
Borrowed$3.59M
Interest paid$868k
Capital taxes average $482k/yr — $131/yr per $100,000 of home value · True cost $7.12M · bonds of $1.87M + $393k · ends 2042 at $41k owns−owes · FY2028 change on a $300,000 home: +$173/yr (+8.8¢ on the rate)
Step up to $530k/yr (by FY2030)
Enter at $450,000, reach a steady $530,000 by FY2030, and let the margin above break-even compound into equity.
Same single-budget structure as the break-even plan, sized past it: two $40,000 steps reach $530,000 and hold. The margin above break-even becomes fund balances rather than interest — the fifteen-year true cost is about $90,000 less than saving $50,000 more a year, and the town ends 2042 owning about $920,000 more.
Raised in taxes, 15 yrs$7.86M
Borrowed$2.88M
Interest paid$736k
Capital taxes average $524k/yr — $143/yr per $100,000 of home value · True cost $6.95M · one bond of $1.81M · ends 2042 at $809k owns−owes · FY2028 change on a $300,000 home: +$149/yr (+7.6¢ on the rate)
Full pre-funding ($535k/yr)
A steady $535,000 capital budget: one town Capital Reserve Fund, and no borrowing after FY2031.
The East Montpelier structure: voters establish one broad Capital Reserve Fund (new money only — the legacy funds spend down on their own purposes), a single bond covers the engine orders, and every later purchase is cash. It carries the smallest bond of any plan, pays the least interest, and exits 2042 with about $1.12 million of equity.
Raised in taxes, 15 yrs$8.05M
Borrowed$2.15M
Interest paid$621k
Capital taxes average $537k/yr — $146/yr per $100,000 of home value · True cost $6.82M · one bond of $1.76M · ends 2042 at $1.12M owns−owes · FY2028 change on a $300,000 home: +$218/yr (+11.1¢ on the rate)
Each dollar not raised for capital is a dollar borrowed at 4% or more while the reserves earn
0.7%. The control below holds the plan structure fixed and varies only the size of a steady
annual capital budget.
More saved, less borrowedOne steady capital budget, set by the slider. Step the budget up and the borrowing and the interest fall.
Borrowed over 15 years$3.70M
Interest paid$889k
True cost$7.14M
Ends 2042 at −$56k owns−owes. Same structure as the break-even plan; only the size of the budget changes. Values from the model's solved grid; the table of all levels is in the downloadable data.
Levy totals alone reward plans that end the window broke. The true cost of a plan is its
fifteen years of tax levies, minus the change in the town's net position — all funds minus
capital debt — from the −$105,243 carried into FY2028, plus the interest its remaining debt
is scheduled to cost after FY2042. That last term matters: the borrowing plans sign notes to
the very edge of the window, and current practice would still owe $82,000 of interest beyond
it. (Post-window earnings on ending fund balances are not credited — debt interest is
contractual; future earnings are not.) Both price bases are shown in the tables:
market-adjusted is the lead; the committee's as-published prices are beside it for fidelity
to the sheet. The base-case spread from current practice to full pre-funding is about
$450,000, and full pre-funding is cheapest in every scenario tested. The structural finding
in the middle of the field: solving for the smallest levy is not solving for cost. The
break-even budget ($480,000) prices about $80,000 worse than the simpler seed plan, and
every step up the steady-budget control above buys more equity per dollar. The step-up plan
states the same point the other way: holding $530,000 from FY2030 costs about $90,000 less
than the seed plan all in, and ends 2042 with about $920,000 more equity. Consolidating all
borrowing into a single twelve-year bond — tested as a stress case — would add roughly
$120,000–150,000 to the middle plans by parking proceeds at 0.7% while the bond costs 4%. Two results hold under every bond structure tested: full pre-funding is the
cheapest of the six plans, and, on the August basis described below, the front-loaded schemes
undercut even it.
The six plans, summarized — full pre-funding carries the smallest bond and the least interest
The six plans
All plans buy the identical equipment on the identical schedule, at market-adjusted prices with apparatus contracts signed three years before delivery. Tax impacts compare each plan's FY2028 capital budget to the $268,022 FY2027 taxpayers already pay for non-flood capital and debt; a $300,000 market-price home is assessed near $196,000 under the current CLA. The flood-recovery debt line (~$466k/yr through FY2031) is identical under every plan and shown separately.
Current practice
FY2028 capital budget $222,681 (−1.9¢ on the rate, −$37/yr on a $300k home)
The town's recent pattern: an inconsistent capital line, funds that sometimes pay and sometimes sit, and full financing for the rest.
The capital appropriation wobbles between $126,000 and $101,000 as it has in recent budgets; a reserve fund pays for an item only when it covers the whole price, as the audit shows; everything else is financed in full — the truck fleet through vendor installment programs, fire apparatus and paving through the plan's capital-program bonds — with debt service riding the tax bill. The culvert plan is paid from the Bridge fund in the years its balance covers the year's pipe, and from the tax bill otherwise. It also keeps feeding the Court Resurfacing fund, which has no scheduled work in the window, and that flatters the position this plan ends with: about $91,000 of its closing balance cannot buy anything on the schedule, so the −$130,000 shown above is nearer −$221,000 of usable capital position, and under 24 V.S.A. § 2804 the money cannot be turned to another purpose without a warned article. Every plan carries the same $18,000 opening balance in that fund; only current practice keeps adding to it.
Average per year, FY28–42
$478k/yr
Interest paid
$997k
Bond issues / financing articles
2 / 12
Owns − owes, 2042
−$130k
True cost*
$7.27M
True cost, sheet prices
$6.10M
Save $50,000 more a year
FY2028 capital budget $272,681 (+0.2¢ on the rate, +$4/yr on a $300k home)
The smallest genuine change: current practice plus a $50,000 annual seed, steered to where the need is.
Same structure as current practice — debt service on the tax bill — but the fund is drawn toward each purchase before borrowing, and the Select Board steers contributions annually to the funds with upcoming needs.
Average per year, FY28–42
$468k/yr
Interest paid
$807k
Bond issues / financing articles
2 / 12
Owns − owes, 2042
−$113k
True cost*
$7.04M
True cost, sheet prices
$5.84M
Phased start from $300k (reaches $480k in FY2032)
FY2028 capital budget $300,000 (+1.3¢ on the rate, +$26/yr on a $300k home)
Begin at $300,000 and climb steeply to the break-even budget of $480,000 by FY2032.
Because apparatus contracts sign years before delivery, the spending crunch sits at the front of this window — so a phased start only works with steep steps, peaking near $681,000 mid-climb before settling. Starting low defers cost at interest.
Average per year, FY28–42
$485k/yr
Interest paid
$860k
Bond issues / financing articles
2 / 12
Owns − owes, 2042
$87k
True cost*
$7.12M
True cost, sheet prices
$5.55M
Break even by 2042 ($480k/yr)
FY2028 capital budget $480,000 (+8.8¢ on the rate, +$173/yr on a $300k home)
A steady $480,000 capital budget — the smallest at which the town owns as much as it owes by 2042.
One annual capital budget inside the budget article, allocated by the Select Board across the existing purpose funds (no new articles needed); the equipment funds pay the equipment notes. Solving for the smallest levy is not solving for cost: the seed plan runs about $80,000 cheaper all in, and every larger steady budget costs less in the end.
Average per year, FY28–42
$482k/yr
Interest paid
$868k
Bond issues / financing articles
2 / 12
Owns − owes, 2042
$41k
True cost*
$7.12M
True cost, sheet prices
$5.51M
Step up to $530k/yr (by FY2030)
FY2028 capital budget $450,000 (+7.6¢ on the rate, +$149/yr on a $300k home)
Enter at $450,000, reach a steady $530,000 by FY2030, and let the margin above break-even compound into equity.
Same single-budget structure as the break-even plan, sized past it: two $40,000 steps reach $530,000 and hold. The margin above break-even becomes fund balances rather than interest — the fifteen-year true cost is about $90,000 less than saving $50,000 more a year, and the town ends 2042 owning about $920,000 more.
Average per year, FY28–42
$524k/yr
Interest paid
$736k
Bond issues / financing articles
1 / 12
Owns − owes, 2042
$809k
True cost*
$6.95M
True cost, sheet prices
$5.48M
Full pre-funding ($535k/yr)
FY2028 capital budget $535,000 (+11.1¢ on the rate, +$218/yr on a $300k home)
A steady $535,000 capital budget: one town Capital Reserve Fund, and no borrowing after FY2031.
The East Montpelier structure: voters establish one broad Capital Reserve Fund (new money only — the legacy funds spend down on their own purposes), a single bond covers the engine orders, and every later purchase is cash. It carries the smallest bond of any plan, pays the least interest, and exits 2042 with about $1.12 million of equity.
Average per year, FY28–42
$537k/yr
Interest paid
$621k
Bond issues / financing articles
1 / 4
Owns − owes, 2042
$1.12M
True cost*
$6.82M
True cost, sheet prices
$5.42M
*True cost = fifteen years of levies minus the change in net position (all funds minus capital debt) from the −$105,243 entering FY2028, plus interest scheduled after FY2042 on debt still outstanding. Each plan bundles its bond-scale needs into a bond sized to the FY2028–31 crunch and drawn within three to four years; plans that bond the Rescue order add a second, smaller question in the mid-2030s. Financing articles are ordinary warned articles for vendor truck installments and five-year bank notes.
Fifteen-year totals by plan — full pre-funding is cheapest in every scenario tested
Fifteen-year totals by plan
Highlight:
Plan
True cost*
Levies FY28–42
Avg tax /yr
Per $100k home /yr
Int. paid
Int. after FY42
Int. earned
Borrowed
Owns − owes 2042
Largest bond
Current practice
$7.27M
$7.16M
$478k
$130
$997k
$82k
$58k
$4.51M
−$130k
$1.89M
Save $50,000 more a year
$7.04M
$7.01M
$468k
$127
$807k
$19k
$36k
$3.27M
−$113k
$1.79M
Phased start from $300k (reaches $480k in FY2032)
$7.12M
$7.27M
$485k
$132
$860k
$39k
$34k
$3.62M
$87k
$1.71M
Break even by 2042 ($480k/yr)
$7.12M
$7.23M
$482k
$131
$868k
$39k
$37k
$3.59M
$41k
$1.87M
Step up to $530k/yr (by FY2030)
$6.95M
$7.86M
$524k
$143
$736k
$5k
$44k
$2.88M
$809k
$1.81M
Full pre-funding ($535k/yr)
$6.82M
$8.05M
$537k
$146
$621k
$0k
$47k
$2.15M
$1.12M
$1.76M
Per-$100,000-home figure: the average capital budget as cents on the rate, on the assessed value of $100,000 of market value at the CLA. *True cost = fifteen years of levies minus the change in net position (all funds minus capital debt) from the −$105,243 entering FY2028, plus interest scheduled after FY2042 on debt still outstanding. Every plan pays the same three inherited notes; the single-line plans route the two equipment notes through the equipment fund while the fire-station bond — which no reserve fund's purpose covers — stays on the tax line. Owns − owes counts every reserve fund, including the Court Resurfacing fund, which has no scheduled work: that overstates the usable position of every plan, and of current practice most, because it alone keeps contributing to it — $91,000 by 2042 against $21,000 for the rest.
Stress tests — the ranking holds under higher rates, no grants, and market-rate reserves
Stress tests
True cost of each plan when one assumption moves. Levy schedules are held fixed; only outcomes change.
Scenario
P0
P1
P2
P3
P5
P4
Base case (market prices, 0.7% earnings, grants)
$7.27M
$7.04M
$7.12M
$7.12M
$6.95M
$6.82M
Reserves moved to a market-rate account (3.5%)
$6.96M
$6.82M
$6.93M
$6.90M
$6.70M
$6.57M
As-published sheet prices
$6.10M
$5.84M
$5.55M
$5.51M
$5.48M
$5.42M
No VTrans grants
$8.26M
$7.99M
$8.34M†
$8.31M†
$8.13M†
$7.76M†
Bond Bank rate at 5.0%
$7.45M
$7.19M
$7.32M†
$7.34M
$7.16M
$6.97M†
Single consolidated bond (12-yr drawdown)
$7.25M
$7.03M
$7.26M†
$7.24M†
$6.95M
$6.82M
Bold green marks the cheapest plan in each scenario. †The plan's fixed levy schedule would run a fund negative under this scenario; a levy adjustment is implied. Plan key: P0 = Current practice · P1 = Save $50,000 more a year · P2 = Phased start from $300k (reaches $480k in FY2032) · P3 = Break even by 2042 ($480k/yr) · P5 = Step up to $530k/yr (by FY2030) · P4 = Full pre-funding ($535k/yr).
Every vote each plan requires, year by year
What voters would be asked, and when
Each plan bundles its bond-scale needs — fire apparatus and major paving — into a bond sized to the FY2028–31 crunch and drawn within three to four years, as federal spend-down rules expect; plans that bond the Rescue order add a second, smaller question in the mid-2030s. Heavy trucks are financed through manufacturers' municipal installment programs and smaller shortfalls through five-year bank notes; both take ordinary warned articles, listed in the downloadable data. Apparatus commits at contract signing, about three years before delivery — Engine 6's order predates this window and is booked at its opening edge.
Six alternative funding schemes were tested against the same rules — same schedule, same
funds, same bond structure — in the same model.
Scheme
Shape
Bond
True cost
Crunch levy
$900k through FY2031, then $450k
$784k
$6.70M
Note ladder
one surge year, three high years, then about $292k; never bonds
none
$6.71M
Crunch-first step-down
seven high years, then today's spend
$1.4M
$6.94M
Steady $650k
break-even structure at $650,000
$1.6M
$6.94M
Bridge and defer
note-bridge FY2028, bond at second need
$852k
$6.91M
State-loan ladder
one state equipment loan (MEVLF) a year on a $515k budget
$1.5M
$7.17M
These six were run in early August 2026, on the schedule as it then stood — before the Class 2
grant rule was corrected to 80% of project cost and before the culvert plan was added — so
their dollar figures are not on the same basis as the plan figures above. The pattern is
uniform: every scheme that beats the plans above shapes the tax ask to the
front-loaded need — high through the engine-order years, stepping down after — and shrinks or
eliminates the bond. On that August basis the two cheapest ran $420,000–430,000 below full pre-funding, and the
note ladder never files a bond question at all, leaving the town's bond capacity in reserve
against the next flood. Their price is concentration: roughly $900,000 a year asked of
taxpayers through FY2031, on top of the flood debt line — about $1.4 million a year all in —
and, for the note ladder, a warned article repurposing the then-idle Bridge and Court Resurfacing
balances. The steady-$650k result restates the structural finding: solved for cost rather
than for the smallest levy, the same structure undercuts every plan above. The state-loan
ladder underperforms because the $150,000 annual cap is small against engine prices and
awards are competitive, not promised.
Each plan needs one or two Australian-ballot bond questions: the FY2028 crunch bond, plus —
for plans that bond the Rescue purchase — a second, smaller question (about
$220,000–450,000) in the mid-2030s. The step-up plan and full pre-funding stop at one. Ordinary
warned articles cover vendor truck installments and five-year bank notes (four to twelve
articles over fifteen years, listed in the tables above and the downloadable data). Because
apparatus commits at contract, the first bond question effectively belongs to the March 2027
warning — before this window opens. A single consolidated bond would trade the second
question for the roughly $150,000–200,000 of parked-proceeds cost priced above.
Prices. Apparatus at commercial-chassis market pricing: the sheet's 2023-vintage figures
escalated 7%/yr to order year (Engine 6 ≈ $655,000 committed FY2028; Engine 1 ≈ $803,000
committed FY2030). The committee's as-published prices are shown throughout for reference;
no contract will sign at them. Everything else is priced in today's dollars — no general
inflation is assumed, so levies are floors, not forecasts: actual future bills rise with
inflation for every plan alike, and the grand list and home values rise with them, leaving
the comparisons and rankings intact. The apparatus escalation is a contract-market fact,
not an inflation forecast.
Known needs only. The schedule prices the replacements the town can already see —
the machines it owns, on their historical cycles. It carries no allowance for new needs,
and fifteen years will bring them; every such dollar arrives on top of every figure
shown, and under the borrowing plans as interest on a larger principal. The charts'
shaded FY2043–52 region is a projection of exactly those known cycles, labeled as such;
no metric is computed from it.
Earnings. The 0.7% base is the town's own realized yield (FY2025 audit); the 3.5%
scenario requires actually moving the money and is labeled as such.
Rates. Bank notes 5.0%; the consolidated bond at a 4.0% Bond Bank assumption — the
actual rate is set at the Bond Bank's sale (the town's May 2025 loan priced at 3.50%); a
5.0% stress column is shown. Vendor truck installments at 5.5% on five-year terms — the
tax-exempt municipal band, with the town's 5.97% excavator note as the local datapoint.
Interest is accrued annually on each instrument's opening balance. The town's notes and
Bond Bank loans in fact pay semi-annually, which lowers a fiscal year's interest by
roughly half a year's accrual on the declining balance — about $1,600 a year across the
three notes carried into the window. Every plan is priced on the same convention, so the
comparisons are unaffected.
Bond structure. Bonds are bundled so each is drawn within three to four years of
issue — standard practice, and what federal tax law expects: 85% of proceeds spent within
three years for unrestricted investment (Treas. Reg. §1.148-2(e)(2)), 85% within five to
keep the interest tax-exempt at all (IRC §149(g)). A single bond sized for twelve years
of projects cannot meet either test, so it appears only as a stress case — its
parked-proceeds cost charged honestly — not as an issuable instrument. Bond Bank access
is open (two pooled sales a year, no fees, no frequency limit; the Bank lent to Middlesex
repeatedly through the flood years); what a second question spends is voter goodwill —
the November 2024 town-hall bond, $2.5 million, failed 610–534. A modest spending tail
beyond three years is routine for bond counsel; the consolidated twelve-year bond is not.
Grants. Class 2 paving awards at 80% of project cost (19 V.S.A. § 309b) — the share
the town applies for and typically receives, confirmed by the Budget Committee in August
2026; they are annual awards, and the no-grants column shows the exposure. No grant is
assumed for the culvert plan: VTrans Better Roads Category D awards (up to $60,000, 20%
match) and the Town Highway Structures program are competitive and unapplied-for.
Shady Rill. The section 1 scope predates the 2023–24 flood reconstruction and must be
re-scoped before any warning article; it remains the largest single line.
Culverts and courts. The Bridge fund now carries the CVRPC five-year culvert plan:
$157,097 of pipe over FY2028–FY2032 for 131 culverts, priced at the town's supplier's
quotes in today's dollars, on top of the roughly $14,000 Culverts line the highway
operating budget already carries for the crew's routine work. Under the reform plans the
fund's annual contribution is sized to it; under current practice the fund pays a year's
pipe only when its balance covers it, and the tax bill carries the rest. Two stream
culverts await hydraulic studies and are unpriced. Bridge maintenance itself is not
scheduled: CVRPC recommends $7,500 a year for the town's two long bridges, each over
$1.5 million to replace. The Court Resurfacing fund still has zero scheduled work — the
sheet, not the town, is missing a court line — so reform plans stop feeding it until the
work is priced; current practice keeps taxing into it.
No major building project. No Town Hall or Town Garage renovation or replacement is
included — the schedule carries only routine upkeep for both buildings ($151,000 and
$19,500 over the window). Any major project, pending the Middlesex FIT proposal and
Select Board endorsement or similar, would be new money on top of every plan shown.
Small items. Purchases at or under $15,000 are cash-flowed inside their fund rather
than financed, which can carry a fund briefly below zero — a payable within a −$15,000
tolerance, never new borrowing. The workbook's fund tables flag any dip beyond it.
Flood debt. The flood-recovery debt is excluded from every plan and identical under
all of them — and it is a bridge, not a lasting burden. Of the $6.4 million on the books
at mid-2025, $4.0 million were notes that matured in 2025–26 while roughly $7.2 million
of FEMA money arrived; the remaining $2.4 million of Bond Bank paper ($466,000 a year of
debt service, stepping to $288,000 in FY2032) is expected to be swept by further
reimbursements. More likely than not there is no net flood levy by about FY2029; the
realistic residual is a one-time $400,000–700,000 of cost shares and compliance work.
The charted flood line is the contractual worst case, standing in full only if the
remaining federal approvals fail. Its debt service can be added to the payment chart
above so no one mistakes the machine notes for the whole bill.
Unconfirmed with the town. The exact warned purpose language of each existing fund
(including whether the Bridge fund's purpose covers culvert pipe), the treasurer's
interest-crediting practice, and a bridge maintenance line are open items; the model's
working inferences are stated with the published data.
Annual votes. Reserve-fund funding votes bind for one year; every multi-year path here
is an annually renewed intention, not a commitment.
The FY2027 base. Tax changes are measured against the $268,022 taxpayers already spend
on non-flood capital and debt in FY2027 — the $126,000 capital line plus that year's four
debt payments: fire station bond $46,817, grader note $25,572, excavator note $27,979 and
the Kenworth note's final $41,654 — not against the capital line alone, because every plan
absorbs those payments as they retire.
The grand list. Cents on the municipal rate are quoted against the 2025 grand list,
where one cent raises about $24,000. A reappraisal is commissioned for 2027; once it is
final the same dollars will read as fewer cents on a larger list. Dollar figures, and what
any household actually pays, are unaffected — a reappraisal is revenue-neutral in aggregate.
Every assumption is tied to a source: 24 V.S.A. §§ 2804, 1786a and 1789 and 19 V.S.A. § 309b
for fund and borrowing law; VLCT's model town-meeting articles and guidance; East Montpelier's
published Capital Reserve Fund practice; the Middlesex 2025 Town Report, the FY2025 audited
financial statements, and the Budget Committee's Capital Asset Inventory FY2026.1; the Central
Vermont Regional Planning Commission's 2026 Road Improvement Plan for Middlesex (July 2026,
with its culvert-by-culvert schedule); and current apparatus-market and municipal-rate data. The model, its inputs, and the code that produces
every figure are published in the site repository; an independent reimplementation of the
stated rules reproduces all results within $2. Fiscal years are July–June; FY2028 is the first
budget a March 2027 town meeting can set.